Before approving a control screen sample, confirm the exact hardware and software versions, then test mounting, power-up, touch operation, controller communication and recovery after an interruption. Record the expected and observed result for each test. Tie the approval to the tested configuration and document any checks that must be repeated before ordering.
Fix the sample configuration and acceptance criteria
Record the panel part number and revision, OS or firmware build, application version, controller firmware, power supply, peripherals and connection settings. Save the approved drawings and interface documents with the test record. If the delivered units may use a different revision, ask what changed and which checks must be repeated.
Write a pass condition for each critical workflow before starting. For example, after restart, the application should display verified current controller status within the project’s agreed recovery time. If the controller is unavailable, the operator should see the defined disconnected state. Use project-specific thresholds and document how each is measured.
Use a representative, authorized fixture. Ask the responsible engineering team which commands and failure cases are safe to exercise and what safeguards the setup needs. Schedule formal system safety and compliance checks separately according to project requirements.
Check physical fit, power and touch
- Fit the sample. Verify the cutout, orientation, mount, cable bend clearance and service access. Check whether connectors remain reachable after assembly. If an ingress rating matters, confirm the mounting and sealing conditions against the supplier’s installation documentation. The Siemens Basic Panels operating instructions show model-specific examples of clearances, seals and supply requirements.
- Power up and restart. Use the approved supply and confirm normal boot with the required peripherals connected. Record time to the point where the operator can use the panel and the device state is verified. Repeat the agreed restart scenarios and record whether settings persist and status refreshes.
- Try the actual controls. Run a setup or operating task in the expected lighting and at the installed viewing angle. Test touch with any required gloves. Include acknowledgements, text entry and controls close together on the display. Record any input that is missed, repeated or hard to read.
Keep the sample photographs, versions and measurements together. A photo of the screen running the app is useful when accompanied by the fit drawing and the precise configuration used during testing.
Run the controller workflow and test recovery
Start with a known status value that can be checked independently. Execute one safe, agreed command and verify its result at the controller or test fixture. Compare the status shown in the application with the actual state. Confirm how the panel distinguishes a request sent, a result confirmed and an error.
- Disconnect and restore communication. Verify that the operator can identify the loss of communication. After reconnection, confirm that the panel refreshes equipment state before it presents dependent controls as available.
- Exercise a timeout or rejected command. On the approved test setup, confirm that the interface shows the agreed error and records enough detail for diagnosis. Check whether a previously attempted command can be repeated, and whether any automatic retry follows the agreed rules.
- Restart one component at a time. Where relevant, restart the panel and controller separately and verify each recovery path. For cloud-connected equipment, agree which functions remain available while the backend connection is down and what happens when it returns.
If a check fails, preserve logs and record the observed behavior before changing settings. Note which panel version, application build, controller firmware and workflow produced the result. This gives the device protocol integration team a reproducible starting point.
Document the decision before placing the order
Use one record per test. Include the requirement, setup and versions, steps, expected result, observed result, evidence, outcome and owner. Keep failed or blocked tests visible. If a sample cannot exercise a requirement, record what remains open and who will supply the missing hardware, documentation or access.
Agree what qualifies for approval, conditional approval or rejection. A conditional approval should identify the change, responsible party, deadline and required retest. Check that the quotation identifies the same configuration tested or documents the differences and associated verification. For hardware still being compared, discuss the sample configuration with the control hardware supply team. For unresolved compatibility issues, define a technical evaluation around the failed or blocked checks.
Include handover items such as the approved build or configuration, interface documents, agreed test evidence and the replacement or deployment instructions. Record which party can reproduce the configuration when the first unit is replaced or updated.
Buyer questions
Can I approve a sample before the final controller is available?
You can record independent results such as fit and display usability. Treat controller communication and recovery as open until verified against representative hardware and firmware or an agreed test setup with documented limitations.
How many times should I repeat the restart test?
Agree the repeat count and pass criteria with the engineering team using the equipment’s expected operating conditions and the consequences of failure. Record every observed failure, even if later attempts succeed.
What should trigger a retest before ordering?
Review any change to the panel revision, OS or firmware build, application, controller firmware, power supply, enclosure or connected peripherals. Repeat the tests affected by the change and record the new approved configuration.